How to design resources in Sequential designer

Post by x4Trace »

How to design resources in Sequential Designer

Open the Production/Sequential Designer menu on the main page to use Sequential Designer.

Select the department, line, and division to design the element and press the "Refresh" button. x4Trace will load all blocks for this line.

Press the "Plus" button to add a Block (Operation) to the designer.
sequentialadddoc.png
sequentialadddoc.png (54.29 KiB) Viewed 562 times
When you add all of the needed blocks (operations), you can edit them (change, move up/down).

To set the order number, press the "Numbered list" button.
sequentialnumberingdoc.png
sequentialnumberingdoc.png (48.98 KiB) Viewed 562 times
x4Trace
Posts: 26
Joined: Fri Feb 14, 2025 2:24 pm

Re: How to design resources in Sequential designer

Post by x4Trace »

Calculate the start and the finish time of blocks (operations)
sequentialsetcalculatedoc.png
sequentialsetcalculatedoc.png (37.19 KiB) Viewed 558 times
1. Fill first operation start time.
2. Select the row.
3. Press the "Calculation" button.

When you press the "Calculation" button, the start and finish times of all blocks (operations) will be recalculated below the selected row. The tasks are automatically generated. To manage the tasks, "like starting the work," you have to open the task manager.
x4Trace
Posts: 26
Joined: Fri Feb 14, 2025 2:24 pm

Re: How to design resources in Sequential designer

Post by x4Trace »

Finish the block

1. Select the block.
2. Press the "Locker" button.
sequentialfinishdoc.png
sequentialfinishdoc.png (37.9 KiB) Viewed 555 times
The selected block will be finished. The date of finish is more than one day later.

3. Press the "Calculate" button to recalculate the blocks below the selected block.
All start and finish dates will be recalculated.